Aoyang Shunchang LED Phase I project completed the finished product gross profit margin of about 40%

On November 5, Aoyang Shunchang announced that as of now, the company's non-public offering of stock funds raised project "LED epitaxial wafer and chip industrialization project (Phase I) (referred to as "LED Phase I Project") has been completed All the 30 major equipment MOCVD and supporting equipments of the project are in place, and the installation and commissioning have been completed. The actual production capacity of the equipment has increased by more than 15% compared with the designed capacity.


According to the plan, the construction period of the first phase of LED project is 30 months. From July 2012 to December 2014, the designed production capacity is to produce 1.8 million pieces of LED epitaxial wafers and chips (equivalent to 2 pieces). At present, the company has formed about 2 million pieces/year of epitaxial wafers and chip production capacity (equivalent to 2 wafers), the capacity utilization rate is close to 100%, and the average sales gross margin of products from January to September is about 40%.


In addition, the company started the construction of LED epitaxial wafer and chip industrialization project (Phase II) in the second half of 2014. At present, the main structure of the plant has been basically completed.

Soccer Ball Air Pump

Soccer Ball Needle,Best Soccer Ball Pump,Football Pump And Needle,Football Ball Pump

SHENZHEN SMARTNEWO TECHNOLOGY CO,. LTD , https://www.newopump.com

This entry was posted in on